Commons Building

Commons Building

Tuesday, June 1, 2010

Project Update

Lessons Learned meetings are continuing. Current issues revolve around litigation being looked at by the college. Review of college responses, related to IT, are ongoing and are expected to be for 2-3 months.

Tuesday, March 23, 2010

Project Update

Lessons Learned Meetings are continuing. No IT issues have arisen.

Wednesday, February 24, 2010

Project Update

All items related to IT's Scope of Work have been completed. Lessons Learned review meetings have been scheduled. Below are the dates for the scheduled meeting:

  • Network Engineering      3/10/10
  • Telephone                     3/25/10
  • Audio/Video                  3/26/10
  • Facilities Applications     3/31/10
  • Intech                           4/08/10
  • Cabling                         4/15/10
  • Full Team Review         4/27/10

Monday, January 11, 2010

Project Update

Interior Cabling

Wireless cabling complete and in production.

Exterior Cabling/Telcom

All exterior cabling complete and tested.

A/V - InTech

SIWS installation complete. PC's for academic systems are in the process of being installed and imaged. SSCC Lab 110A table deficiencies have been corrected. Still awaiting delivery of PC mounts for SSCC Lab 110A from Central Facilities vendor.

Network Infrastructure

IMCnet, MCnet, MCFnet infrastructure complete.

Tuesday, December 1, 2009

Project Update

Interior Cabling

All General Contractor interior supplied cabling has been completed. Wireless cabling to begin the second week of December (Estimated)

Exterior Cabling/Telcom

Lightning protection modules have been changed to the correct module. Exterior cabling complete.

A/V - InTech

SIWS installation as well as conference room installations almost complete. Currently waiting on Facilities supplied credenza's. PC's set for deliver Dec 1st or 2nd.

Network Infrastructure

IMCnet and MCnet infrastructure installed and tested. Once Wireless infrastructure has been installed all network infrastructure will be complete.

Thursday, October 22, 2009

Project Update

Interior Cabling

Interior cabling complete and punch list items still being corrected. The only major item left is the missing room numbering on patch panels within the MDF & IDF.

Exterior Cabling/Telcom

Lightning protection modules being changed out on copper cabling to accomodate college voice communications. Estimated time until install of the correct lightning protection circuit breakers is about 3 weeks.

A/V

Mediatech/Dell quote has been submitted for approval by IT Administration. Current estimated start time for Mediatech installation is November 15th.

Network Infrastructure

IMCnet and MCnet infrastructure awaiting interior punch list item completion before work can be completed. All switch gear is in place and powered however until the punch list items are complete testing cannot be completed.

Monday, September 14, 2009

Project Update

Interior Cabling

Interior cabling complete and punch list items being corrected.

Exterior Cabling/Telcom

Exterior cabling complete. Lightning protection modules being changed out on copper cabling to accomodate college voice communications. Estimated time until install of the correct lightning protection circuit breakers is about 4 weeks.

A/V

Mediatech/Dell quote is currently being revised and prepared for submission. Mediatech install to commence October 15th. Previously approved construction contractor supplied projection screens have been found to be deficient and alternatives are being reviewed.

Network Infrastructure

MCFnet infrastructure complete and IMCnet and MCnet infrastructure as well as wireless access points set for installation to begin September 28th.