Interior Cabling

Interior cabling is continuing and shall be completed this week.

Exterior Cabling

Outside Service Plant cabling (Fiber/Coax/Copper) has been run and is being terminated at both SSC and Commons MDF's. Work to be completed this week.

A/V

Mediatech/Dell quote is currently being revised. Conference room credenza's are being reviewed for compliance with college A/V standards and use. Previously approved construction contractor supplied projection screens have been found to be deficient and alternatives are being reviewed.

Network Infrastructure

P.O. has been sent to the sub-contractor and Infrastructure installation currently planned for the week of August 17th.